The Siripadaya Construction Project is progressing steadily under the close supervision of Directorate of Engineer Services, in accordance with approved designs and safety standards. The 300 m wall has been fully completed, while construction of the 500 m wall has reached approximately 65% completion. Work on the main 8-foot wall is currently underway, with around 20% completed.
With the timely availability of materials at the site, Engineer Services Regiment, in collaboration with other regiments, is scheduled to complete the project before 1st January 2026.